Your browser does not support Javascript

$17.2 Million in Renovations to Schools this Summer/Fall

July 06, 2017

Mayor Domenic Sarno, Superintendent Daniel Warwick, and city officials announced the proposed $17.2 million in summer work across the city’s school facilities. With funding from both the city and Massachusetts School Building Authority (MSBA) over $17.2 million in renovations will be invested over the course of this summer through the fall of 2017.  The work has been part of a school renovation plan set in place by Mayor Sarno and School Committee five years ago.

SCHOOL BUILDING PROJECT LIST

SUMMER 2017

SCHOOL AND PROJECT

AMOUNT

 Berkshire restroom upgrades 

              30,000.00

 Central Lighting Upgrade 

           104,969.00

 Central press box repair 

              48,000.00

 Chestnut Cooling Tower 

           139,000.00

 Commerce  Pumps/Chiller Tower Replacement 

           296,564.00

 Commerce flooring upgrades 

              93,497.66

 Commerce Lockdown Hardware Upgrade

              47,000.00

 Commerce Painting 

              32,000.00

 Design and  Monitoring of Abatements 

           105,240.00

 Dorman Fire Alarm

           108,300.00

 Duggan Auditorium Finish Improvements 

           233,451.00

 Duggan Fire Alarm 

           437,025.00

 Duggan Flooring Installation 

           103,238.00

 Duggan Gym Floor Replacement 

           201,856.00

 Duggan restroom upgrades 

              40,971.00

 Duggan Underground Storage Tank Removal 

              28,398.00

 Duggan VAT abatement 

           109,000.00

 Early Childhood Boilers 

           159,000.00

 Early Childhood Roof

           259,000.00

 Freedman Fire Alarm

           101,000.00

 Freedman- Lockdown Hardware Upgrade

              34,000.00

 Gerena/Central CW/CW Pump Replacement 

           109,000.00

 Glenwood- Paint entire school 

              44,120.00

 Glenwood- Remove Oil Tank 

              31,450.00

 Moving Services for projects

              39,000.00

 Pottenger- Boiler Room Sump Pump 

              37,000.00

Sci-Tech Chillers Control Upgrade

              44,230.00

Stem Field Installation

           129,000.00

 Various Locations- Old TV removal 

              73,050.00

 Various Locations- Paving Improvements 

           198,000.00

 Glenwood Parking lot 

 

Margret Ells Improvements 

 

Mary Lynch Improvemets

 

          Stem Resurfacing of BBall courts

 

          Freedman- Dumpster pad/ area Install

 

Walsh crawlspace- TSI abatement

              69,000.00

 Walsh Lockdown Hardware Upgrade 

              34,000.00

 Walsh- Steam trap/ line repair 

              34,000.00

 Estimated Total Current Project Value 

 $    3,553,359.66

   

MSBA PROJECT

 AMOUNT

 Brunton new windows and doors,ADA upgrades

        2,662,470.00

Balliet Rosewell new roof and ADA upgrades

        2,117,130.00

Kensington new roof and ADA upgrades

        1,488,913.00

Lynch new roof and ADA upgrades

           990,659.00

 Public Day High school new windows and doors, ADA Upgrades

        1,690,807.00

STEM  structural upgrades and new roofing system

        2,103,396.00

Walsh new windows and doors ADA upgrades

        2,646,869.00

 Estimated Total Current Project Value 

 $  13,700,244.00